Respuesta :
Answer:
Profitable sales mix :
Deluxe - 180,000 units,
Classic - 58,500 units,
Basic- 365,000 units
Explanation:
When a business is faced with a problem of shortage of a resource which can be used to produced more than one product type, to maximize the use of the resource , the business should allocate the scare resource for production purpose in such a way that it maximizes the contribution per unit of the scare resource.
The labour hours required per unit of scarce resource=
Basic   = 1/10 hr=  0.10
Classic =1/8 hr   = 0.13     Â
Deluxe= 1/4  hr  = 0.25
                         Basic        Classic      Deluxe
Contribution per  unit          15            25         55
Hour per unit               0.10           0.13        0.25
Contribution per hour        150            200         220
Product     Unit                     Hours used
Deluxe     180,000   180000×  0.25     45,000
Classic     468,000  468,00×  0.13      58,500
Basic       365,000**   365,000×0.10    36,500*
Total hours                             140,000
* Â = 140,000 - 45,000-58500= 36,500 hours
** Â = 36,500 hours/0.1 hour = 365,000 units
Units to be produced = 36,500/0.10= 365,000 units
Profitable sales mix :
Deluxe - 180,000 units,
Classic - 58,500 units,
Basic- 365,000 units
Â